August – October 2021


Moscow CHPP-27 – a branch of PJSC “Mosenergo”

Works on dismantling and installation of the generator stator with a mass of 175 tons in the cramped conditions of the operating turbine hall No. 2 of CHPP-27 were carried out without dismantling pipelines and service platforms up to the level of +6,000. Above the stator of the generator is the Integrated Air Purification Unit.