2018 – 2019


Zapolyarny

In 2018-2019 JSC “Titran” performed works on the installation of a lean concentrate enrichment shop at the facility – the enrichment plant. Concentrate offloading unit at the site of the Kola MMC Enrichment Plant, Zapolyarny.

More than 60 pieces of equipment were installed, including:

  • The body of the lean concentrate thickener with a diameter of 20 meters was welded.
  • At the same time, our specialists deduced its geometric parameters exactly to the requirements of the equipment supplier – Outotek company – a tolerance of 19 mm.
  • A press filter, conveyors, bridge cranes, compressors, wagon and container scales and many other pieces of equipment were installed.
  • All installed equipment was commissioned, tested and handed over to the Customer – the Kola MMC.